The targeting of industrial energy audits for DSM planning

Authors

  • M I Howells Energy Research Centre, University of Cape Town

DOI:

https://doi.org/10.17159/2413-3051/2006/v17i1a3313

Keywords:

electricity consumption, demand side management, industrial energy audits, energy saving, energy audits, payback periods

Abstract

The scope of this section of the study is to establish which industries to target for energy audits and demand side management (DSM) projects. As only a limited number of audits will be conducted, it is important to establish how to maximise the return on the invested efforts and resources. The aim is thus, to develop a ranking of industries based on their potential for savings from DSM interventions. It considers the following criteria: 1. Electricity consumption and potential DSM savings from retrofits at existing plants; 2. Electricity consumption and potential DSM savings for new plants; 3. Potential DSM interventions by industry; 4. The costs of a suite of DSM interventions by industry; and 5. The technical ease with which DSM may be implemented by industry. The potential for DSM savings for different industrial sectors is evaluated based on these criteria, using aggregated values sourced from local and international studies. DSM measures are applied to the various ‘end uses’ of electricity within each industry. From these we suggest a shortlist of 10 industries to target for energy audits and data gathering. We consider both industry and mining, and refer to the group collectively as industry. The data gathered in the energy audits will be used to refine estimates of the potential for DSM savings in each sector. Data loggers will be installed to measure electricity consumption and demand profiles (kW load as a function of time), which will be used to estimate the impact of DSM interventions on national demand for energy and power. This can provide valuable input to power system planning and analysis in the future.

Downloads

Download data is not yet available.

References

EIA 2004, Energy Information Administration,

www.eia.gov , 2004.

DTI 2004, Department of Trade and Industry,

http://www.eia.doe.gov/emeu/mecs/mecs94/consumption/mecs5.html#mecs2cb www.dti.gov.uk/energy/bluebook/pdf/appendix2.pdf,

Howells et. al. (2002), Howells, M., Solomon, M. and

Kenny, A. Energy Outlook 2002, for the Department

of Minerals and Energy, Energy Research Institute

Gildenhuys, A. (2003), Senior Engineer, Integrated

Strategic Electricity Planning (ISEP) Office, ESKOM,

personal communication, 2003.

NER (2003), The National Electricity Regulator, ESKOM

and the Energy Research Centre, The National

Integrated Resource Plan, www.ner.org.za 2004.

Kenny A. et al (2000a), Kenny, A., Howells M. I. and

Drummond R., Energy Management News. ‘South

African Breweries energy audit case study’. Outlines

an energy audit case study undertaken by ERI, TSI,

NOVEM and AEAT at SAB’s Propecton plant,

September 2000.

Kenny A. et al (2000a), Kenny, A., Howells M. I. and

Drummond R., Energy Management News. ‘SAPPI

energy audit case study’. Outlines an energy audit case study undertaken by ERI, TSI, NOVEM and

AEAT at the SAPPI Mandini Mill, September 2000.

Kenny A. et al (2000a), Kenny, A., Howells M. I. and

Drummond R., Energy Management News.

‘Elandsrand energy audit case study’. Outlines an

energy audit case study undertaken by ERI, TSI,

NOVEM and AEAT at Anglogold’s Elandsrand gold

mine, September 2000.

Howells M.I. and Laitner J. (2003), ‘A technical framework

for greenhouse gas mitigation in developing

countries’, Summer Study, American Council for an

Energy Efficient Economy, 2003.

Downloads

Published

2006-02-01

How to Cite

Howells, M. I. (2006). The targeting of industrial energy audits for DSM planning. Journal of Energy in Southern Africa, 17(1), 58–65. https://doi.org/10.17159/2413-3051/2006/v17i1a3313